Following are highlights of OC Go’s projects and programs during the first three months of 2022:

  • Work progressed on the I-5 Improvement Project in South Orange County, which is scheduled for completion in 2024, and the I-405 Improvement Project, which is expected to fully open to traffic late next year. 
  • A consultant was selected to prepare plans, specifications and estimates for future improvements to SR-55 between I-5 and SR-91. 
  • Construction continued on the OC Streetcar project, including the placement of the first embedded track-slab concrete on Fourth Street, installation of ballasted track between the Westminster and Santa Ana River bridges and installation of the first steel structures for the maintenance and storage facility. 
  • A call for projects was released through the environmental cleanup program, which awards money on a competitive basis to cities and the county for projects that reduce the impacts of water pollution related to transportation. Since 2011, the program has allocated more than $54 million to projects that have captured an estimated 45.3 million gallons of trash. 
  • Ridership on Metrolink trains continued to trend positively, with total boardings on the Orange County line increasing on average by more than 100% compared to the same quarter last year. OC Go is the primary funding source for Metrolink service in Orange County.