OCTA has declared an emergency and authorized CEO Darrell E. Johnson to take the necessary actions to protect the railroad track near a sliding hillside in San Clemente.
OCTA is working with Metrolink to develop and implement protective measures along the rail line, below Casa Romantica Cultural Center and Gardens just north of the San Clemente Pier, to allow the rail line to be reopened for safe passenger rail service as soon as possible.
That effort will likely include designing and constructing a temporary barrier wall at the bottom of the slope, within the rail right of way owned by OCTA. The purpose of the temporary wall would be to keep any additional debris from the slide from interfering with safe passenger rail movement on the track. Metrolink is expected to hire a contractor to design and build the wall on an emergency basis to speed up construction.
At the same time, the city of San Clemente is leading efforts to determine the cause of the slide and to stabilize the hillside above the track. The city has indicated that effort will take several weeks but has not given a more detailed timeline.
There is no timeline yet to resume rail service. That decision will be made when OCTA, Metrolink and the LOSSAN Rail Corridor Agency, which operates Pacific Surfliner service, jointly determine that it is safe for passenger rail travel to resume.
“As always, passenger safety will guide every action we take,” OCTA CEO Johnson said. “We understand how difficult this closure is for the people who rely on rail service through San Clemente and we will work hard to get service running again safely.”
The initial slide near Casa Romantica occurred on April 27, sending debris into the rail right of way and forcing a stop to all passenger rail service. The city of San Clemente worked with geotechnical experts and with a contractor to grade and stabilize the slope. Passenger rail service had resumed through the area on May 27.
However, on June 5, the hillside significantly slid again, sending debris, including large clumps of dirt and a tree, into the area near the tracks below, forcing another indefinite stoppage of rail service. Two days later, on June 7, freight rail traffic resumed – at a significantly reduced speed of 10 mph. But Metrolink, along with OCTA and LOSSAN, determined that, out of an abundance of caution, passenger rail service should remain halted until more significant measures can be taken to protect the track.
The rail partners will work with the California Coastal Commission for emergency permitting for the temporary barrier wall. The size of the wall will be determined at a later date, in consultation with an engineering contractor.
The location of the falling debris near Casa Romantica is approximately 2 miles north of where OCTA is completing construction work to secure another hillside near the Cyprus Shore Homeowners Association in San Clemente. This instance of falling debris from the Casa Romantica hillside is unrelated to that effort.
Currently, Metrolink regional passenger rail service is operating as far south as San Juan Capistrano on weekends, while weekday Metrolink service will continue to operate only as far south as the Laguna Niguel/Mission Viejo Station until further notice.