Orange Freeway Construction Moves Forward

Construction crews continue to move forward on all three segments of the State Route 57
(SR-57) Freeway Improvement Project
.
 
On the project's northern segment, which spans approximately Yorba Linda to Lambert, crews are wrapping up a number of punch list items, including fiber optic, irrigation and signage work.
 
On the central segment, the construction team is finalizing work on a number of ramps, lanes and walls located adjacent to the cities of Fullerton and Brea.
 
In the southern segment, crews are currently working on lane operations from approximately Katella to Lincoln. The work, which will be ongoing for the next two weeks, includes soil compaction, importing of base materials and concrete pours and lane paving operations.
 
Funded by Measure M, the $150 million project will deliver a new eight-mile northbound lane and several other operational improvements along this corridor that connects motorists to various residential communities, employment centers and entertainment destinations. Click here to learn more.